News Center

CWE Wins Bid for the Bonaberi High-Voltage Substation Project in Cameroon

Release time:2024-07-10

 On July 5, CWE received a bid acceptance letter from the Cameroon National Electricity Transmission Company, successfully winning the bid for the high-voltage substation project in Bonaberi, Cameroon.
The project primarily involves the upgrading and retrofitting of existing equipment at the substation. It includes the supply, transportation, installation, connection, and operation of two 90/15 kV - 50 MVA three-phase power transformers, as well as the design and provision of new transmission room equipment.
The implementation of this project will significantly enhance the local power grid’s interconnectivity, reduce electricity transmission losses, and alleviate power supply issues in the surrounding areas, thereby injecting a strong impetus into the local economic development.